If you follow my blog you
undoubtedly follow the two Facebook pages ‘Lost Ingham and District’ and ‘District
Archival History’ which are hosted by two other ladies keen on unearthing and sharing Ingham's history. In the last couple of weeks they have been theming floods
and cyclones. With so much water everywhere – rivers, creeks, streams, waterfalls
and regular floods and annual monsoonal downpours it seems strange to think
that a clean, healthy water supply for Ingham and its outlying communities has
not always been a given.
Households in early Ingham town
had their own private wells, while there was also a town well. But cesspits for
human waste contaminated these wells causing sickness and the threat of
epidemics. The introduction of a nightsoil service helped lessen the
incidence of wells being contaminated by cesspits, but even so the
Council was acutely aware that this was not a long term solution. As the town
grew there was an increasing number of private homes, public buildings and
factories which increased the chances of the town well becoming contaminated with
effluent. Two health
concerns that persisted well into the twentieth century were typhoid and hookworm
and these were only brought under control with an improvement in sanitary
conditions.
The Health
Department inspector recommended that a water supply be taken from the Herbert
River. As a result C.E. Deshon, an officer of the Department concerned with water
supplies, was invited to report to the Council on a suggested scheme. His
findings recommended a water tower to supply 45 000 gallons, sufficient for
around 1 500 people, which would cost £8 957. At this point the Council did not act despite the
disastrous performance of the town well during the 1915 drought. The water
level dropped so low that the pump was unable to work, and water had to be
carted from the river. The result was, as could be expected, considerable
sickness due to contaminated water.
It was twenty
years before the town water problems were finally solved. Jack Mulholland, consulting
engineer, guided by Irrigation Department's plans, recommended that the Council
apply for a loan of £36 750 with a 50% subsidy similar to that granted for
other water schemes. The subsidy would
have been £8 000, but it was determined that the Council would pay only a third
of the cost while the other two-thirds would be contributed equally by the
State and Federal governments. This was a ground breaking offer and the first
grant of its kind for a water supply. Work began in May 1937 and proceeded
using the unemployed as day labour to lay pipes.
Work involved construction of a concrete well at the intake
on the Herbert River, a concrete tower 120 feet high in the centre of Ingham,
mains between those points and reticulation pipes throughout the supply area
with consumer connections being the householders' responsibility. In July 1938 water began to be supplied with
the aid of pressure valves until the tower was ready. The new supply was first
available for limited hours, which became more generous as the number of consumers
increased. The scheme was finally completed in March 1939 with nearly 500
consumers already connected and extensions being planned soon after.
The introduction
did not go without teething problems. Experimental fibrolite pipes leaked, excessive
consumption had to be checked because though the source of supply, the river,
was boundless, delivery was restricted by the capacity of the power house
plant. Water restrictions were imposed during periods of heavy consumption,
particularly during the war when electricity generation was reduced. Excessive domestic
use was curbed by house to house inspections looking for leaking taps,
educating consumers and even prosecuting where flagrant waste occurred.
The water was cleaned
by natural filtration through sandbanks in the river bed and generally the
quality was good. However the supply was vulnerable to discolouration which occurred
when floodwater from the river entered the pump well or if there were dredging operations
in the upper Herbert. Rusting of the pipes was caused by significant numbers of
bacteria releasing large amounts of carbon dioxide. A chlorinator was installed
to treat the water which largely solved the problem.
The supply was received
so well by the community that within the year there were requests for
extensions from Trebonne, Halifax and Victoria Mill but the looming war put a
hold on such plans. The concrete tower itself, a 120 feet high structure, was now
however, the highest structure on the skyline and would be clearly visible to
enemy warcraft. This caused some consternation in the Council chamber. There were some councillors who argued that
the tower should be camouflaged, but not all agreed. In the end, shortages of both labour and paint
put paid to the idea.
Sources:
Vidonja
Balanzategui, Bianka. The Herbert River
Story. Ingham: Hinchinbrook Shire Council, 2011.
Wegner, Janice. “Hinchinbrook:
the Hinchinbrook Shire Council, 1879-1979.” MA diss. James Cook University,
1984.
Wegner,
Janice. “Hinchinbrook Shire during World War Two,” Lectures on North Queensland History,
https://espace.library.uq.edu.au/view/UQ.../Lectures_on_NQ_History_S4_CH11.pdf.
Source: State Library of Queensland. 2211512. Large Water Tower, Ingham Queensland, 1953 |
Source: Hinchinbrook Shire Library Photographic Collection. Herbert Street during 1967 flood |
Source: Hinchinbrook Shire Library Photographic Collection. Aerial photo of Herbert Street 1971 |
Source: Hnchinbrook Shire Library Photographic Collection, Aerial photograph of Ingham during 1977 flood |